Building & Zoning

Zoning & Planning

Steps for Level Two Site Plan

  1. Pre-application conference with the Zoning Administrator.

  2. Applicant submits application, fees & 17 copies of preliminary site plan to Zoning Administrator, who reviews plan and transmits, to Planning Commission with an analysis.

  3. Planning Commission reviews preliminary site plan. Planning Commission approved, approves with modifications or disapproves preliminary site plan (may establish conditions).

  4. Upon approval of preliminary site plan, applicant submits final site plan to Zoning Administrator within 6 months.

  5. Applicant submits final site plan and posts a bond or cash deposit for the cost of public improvements for the project (if any). Zoning Administrator has 90 days to approve the final site plan. Approval of final site plan expires in 1 year (unless building permit obtained).

  6. Applicant submits an Erosion & Sediment Control Plan permit application and fees. Review by Wetlands Engineer and determine bond amount for erosion control measures. Approves or disapproves plan within 45 days. If approved, pre-construction meeting set with Wetlands Engineer and Zoning Administrator. Land disturbance permit is issued – start construction. Periodic monitoring of project by Wetlands Engineer and Zoning Administrator.

Zoning Fees

Land Development Application — This form is in Acrobat (pdf) format. If you do not have a copy of Adobe’s Acrobat Reader currently installed on your computer, click here to install it.